Payment Process:
Payment Process Overview

3. Execute a Frequency Reconfiguration Agreement (or Planning Funding Agreement) with Sprint Nextel

If you require funding for planning activities after you submit a Request for Planning Funding, you will negotiate a Planning Funding Agreement with Sprint Nextel. For your actual system reconfiguration, after you submit a Cost Estimate (and SOW for complex systems), you will negotiate a Frequency Reconfiguration Agreement with Sprint Nextel governing the terms of your reconfiguration. You will be required to certify that the costs estimated on your Request for Planning Funding and/or Cost Estimate are the minimum necessary to provide facilities comparable to those presently in use.

Once you and Sprint Nextel have reached an agreement, sign the FRA (or PFA) and return it to Sprint Nextel. The TA will then review your Cost Estimate (or Request For Planning Funding), Frequency Reconfiguration Agreement (or Planning Funding Agreement), and supporting documentation in a timely manner and will:
Approve it
Reject it (and provide reasons and/or recommendations)
Request additional information
Once the TA approves your Cost Estimate (or Request For Planning Funding) and signed Frequency Reconfiguration Agreement (or Planning Funding Agreement), Sprint Nextel will sign and finalize the Frequency Reconfiguration Agreement (or Planning Funding Agreement). For more information, please refer to the section of this Handbook entitled "Negotiate the Frequency Reconfiguration Agreement with Sprint Nextel."

4. Submit Change Notice, if necessary

As your planning and reconfiguration activities proceed in accordance with the work described in your PFA or FRA, there may be a need for changes to the scope of such work. These changes may occur at any point in the planning and reconfiguration process between the time that you execute your TA-approved PFA or FRA with Sprint Nextel and the time that you reconcile your costs with Sprint Nextel prior to the contract closing. Whenever a change to your PFA or FRA scope of work is required, you will need to submit a Change Notice in accordance with the applicable terms of your PFA or FRA, negotiate the Change Notice with Sprint Nextel, and submit it to the TA for review and approval. For more information on the Change Notice, please visit the TA's website (http://www.800TA.org/content/documents/change_notice.asp).